Greek Street roundabout in Edgeley, Stockport is located on a bridge that runs over the railway.
From 31 March this year [2025], until Spring 2026, Network Rail will be carrying out work to install a new railway bridge and roundabout. Timescales of the phased work are summarised below:
- In August 2025, Network Rail will need to close the railway in Stockport for 21 days. During this time, work will take place to remove the old bridge and install the new one.